LIST OF NOTABLE PROJECT

CustomerProjectYear of
Completion
Camarines Sur II Electric
Cooperative, Inc.
69kV Transmission Lines & 13.2kV Double-Circuit
Distribution Lines at Naga North and Naga South
2016
Northern Samar Electric
Cooperative, Inc.
Rehabilitation of 5MVA Allen Substation 2017
Gendiesel Philippines Inc. Installation, Testing and Commissiong of 1-2MVA
MTU Genset
2017
Aboitiz Energy Solutions, Inc. Retirement of LV and MV Capacitor Banks 2018
Central Luzon State University Emergency Replacement, Supply and Installation of
Medium Voltage Switchgear
2018
Pampanga II Electric
Cooperative, Inc.
Rehabilitation and Uprating of 33MVA, 69kV
13.2kV, Mabiga Substation
2018
NLB Enterprises Suppy and Installation of Medium Voltage
Switchgear for Dayao Substation
2019
Hyosung Heavy Industries
Philippines
Preventive Maintenance and Gasket Replacement of
2-300MVA, 230kV-69kV, Power Transformer at
NGCP Mexico and NGCP Cabanatuan
2019
Capiz Electric Cooperative, Inc. Construction of 3.26km, 69kV, Lawaan-Dayao
Transmission Lines
2019
Point 8 Prime Construction and
Consultancy Inc.
Luzon Voltage Improvement Project 3, Stage 1,
Schedule I at NGCP Tuguegarao
2019
Manila International Airport
Authority
Supply, Installation, Testing and Commissioning of
Medium Voltage Switchgear
2019
Angeles Electric CorporationSupply, Installation, Testing and Commissioning of
12-cubicle Medium Voltage Switchgear at Milenyo
Substation
2019
NLB EnterprisesConstruction, Installation and Testing of 25MVA,
69kV-13.2kV, Dayao Substation
2019
Pampanga II Electric
Cooperative, Inc.
Relocation of 10MVA, 69kV-13.2kV, Power
Transformer from Mabiga Substation to Guagua
Substation
2020
Hyosung Heavy Industries
Philippines
Assembly, Testing and Commissioning of 200MVA,
500kV-230kV-13.8kV, Power Transformer at NGCP
Tayabas
2020
Camarines Sur II Electric
Cooperative, Inc.
Construction, Supply, Installation, Testing and
Commissioning of 25MVA, 69kV-13.2kV, Pili
Substation
2020
Pampanga II Electric
Cooperative, Inc.
Emergency Replacement of 10MVA, 69kV-13.2kV,
Power Transformer at Santa Cruz Substation
2020
Hyosung Heavy Industries
Philippines
Repair of 100MVA, 230kV-69kV, Power Transformer
at NGCP Mexico
2021
Pampanga II Electric
Cooperative, Inc.
Rewinding of two (2) units 10MVA, 69kV Power
Transformer at Sta. Cruz Substation and Pio
Substation
2021
Pampanga II Electric
Cooperative, Inc.
Emergency Replacement of 25MVA Power
Transformer Due to High Combustible Gases
2022
Maxipower Sales & Services
Corporation
Preventive Maintenance of Transformer at
Northern Cement Corporation
2022
JGC Philippines, Inc. Testing of Medium Voltage Station at
Cayanga-Bugallon Solar Power Pangasinan
2022
Sorsogon I Electric Cooperative,
Inc. (SORECO I)
Testing and Commissioning of 5/6.25MVA Power
Transformer
2022
Northern Samar Electric
Cooperative, In (NORSAMELCO)
Supply, Installation and Commissioning of
20/25MVA Power Transformer at Bobon Substation
2023
Pampanga I Electric
Cooperative, Inc. (PELCO I)
69kV Gantry and Disconnect Switch Support
Structure
2024
First Gen Hydro Power
Corporation
Regasketing of 1-unit 64MVA Power Transformer
Pantabangan Hydroelectric Plant
2024